Your project · Kitchen remodel
Kitchen remodel
Now: Finishes · Start Wed, Nov 25 · Finish Wed, Dec 2
- Design visit
- Proposal
- Selections
- Permit
- Demolition
- Rough-in and inspections
- Finishes
- Walkthrough
- Done
Step 7 of 9: Finishes
Waiting on you
Updates
-
Fri, Nov 27
Cabinets delivered and checked against the order. Install starts Monday.

Sample photo -
Thu, Nov 26
Rough-in passed inspection today: electrical and plumbing.

Sample photo -
Tue, Nov 24
Demolition done. Dust walls up, floors covered.

Sample photo -
Thu, Nov 19
Proposal accepted by Owen K.
Payments
- DepositDesign and permit drawings$4,510Paid Thu, Nov 19
- Demolition doneWhen the old kitchen is out$11,275Not paid yet
- Rough-in passedAfter the inspection passes$11,275Not paid yet
- Cabinets and counters inWhen the cabinets and counters are in$11,275Not paid yet
- FinalAfter the walkthrough$6,765Not paid yet
Before the final payment
At the walkthrough, list anything left to fix. The final payment waits until the list is done.
Your accepted proposal
Accepted by Owen K. on Thu, Nov 19. This copy doesn't change.
- Design and permit drawings$2,500
- Demolition and haul-awayDust walls and floor protection$3,200
- Electrical and plumbing rough-inNew circuits, sink and dishwasher lines$8,500
- Cabinets, installedPlywood boxes, soft-close, 24 ft$16,800
- Quartz countertops3 cm, 55 sq ft, one undermount sink$6,400
- Tile backsplash$2,200
- FlooringLuxury vinyl, 240 sq ft$2,900
- Paint and trim$2,600
Total$45,100
- Cabinets
- Plywood boxes, soft-close doors and drawers
- Counters
- 3 cm quartz
- Electrical
- To code, 2 new circuits
- Selections